The table below provides details of the scheduled activity for the implementation of TradElect.
|
Activity |
Timing |
|
Customer Technical Seminars |
17, 20 and 26 July 2006 |
|
New CDS + Conformance available |
9 October 2006 |
|
Mandatory Conformance testing available |
6 November 2006 |
|
New EAS available |
Service decommissioned 16 March 2007 |
|
Technical Specifications updated |
December 2006 |
|
Live Market Configuration Document |
April 2007 |
|
Dress Rehearsals |
28 April, 19 May and 2 June 2007 |
|
Go Live |
18 June 2007 |